Oracle Primavera - PM6 Member for 19 years 3 months Member for 19 years 3 months Submitted by Suresh Sankara… on Thu, 2008-04-24 04:47 Permalink RE: RESOURCE DRIVING PROJECT Dear Imaran, Thank you very much. Yup that is the one i forgot.. "Instead of Task Dependent" we suppose to give " Resource Dependent" Many many thanks. Suresh Member for 18 years Member for 18 years Submitted by Imran Arshad on Thu, 2008-04-24 04:42 Permalink RE: RESOURCE DRIVING PROJECT Dear Suresh, For resource driven project setting got to project window,click on Defaults tab then define percent complete as Units & activity type as resource dependent before adding activities in your project.Hope this will help. Imran Arshad Log in or register to post comments
Member for 19 years 3 months Member for 19 years 3 months Submitted by Suresh Sankara… on Thu, 2008-04-24 04:47 Permalink RE: RESOURCE DRIVING PROJECT Dear Imaran, Thank you very much. Yup that is the one i forgot.. "Instead of Task Dependent" we suppose to give " Resource Dependent" Many many thanks. Suresh
Member for 18 years Member for 18 years Submitted by Imran Arshad on Thu, 2008-04-24 04:42 Permalink RE: RESOURCE DRIVING PROJECT Dear Suresh, For resource driven project setting got to project window,click on Defaults tab then define percent complete as Units & activity type as resource dependent before adding activities in your project.Hope this will help. Imran Arshad
Member for
19 years 3 monthsRE: RESOURCE DRIVING PROJECT
Dear Imaran,
Thank you very much. Yup that is the one i forgot.. "Instead of Task Dependent" we suppose to give " Resource Dependent"
Many many thanks.
Suresh
Member for
18 yearsRE: RESOURCE DRIVING PROJECT
Dear Suresh,
For resource driven project setting got to project window,click on Defaults tab then define percent complete as Units & activity type as resource dependent before adding activities in your project.Hope this will help.
Imran Arshad