Problems when exporting from Primavera to MS Project

Member for

20 years 6 months

Dieter



You are right (again)I have been trailing importing from MSP to P6 on some sample projects. When the project is just logic driven it seems to work fine (except the issue with the milestone ’duration’) but if you try to add constraints it gets messy.



Thanks again, it is appreciated, Sunny does any of this make sense/assist?



Regards



Brian

Member for

20 years 6 months

Deiter



Thanks for the advice, I believe the problem may be confined to version 6.0 and is fixed in 6.1.



This problem may be contributing to the problems Sunny encountered importing from P6 to MSP (date variances etc.)



Regards



Brian

Member for

20 years 6 months

I am not sure if this helps, I have had a similar problem but when in importing projects from MSP to P6. For example in MSP a finish milstone would show the same completion date as it’s predessor, in P6 the finish milestone can jump to the following day.



Instead of the finish milestone having ’no duration’ P6 assigns a small duration which appears to cause the problem.





I hope this makes sense & helps.



Regards



Brian




Member for

18 years 9 months

Sunny

P5 and P6 shouldn’t produce a significant difference for the dates against the MSP schedule (2000 or 2003). With 2007 I have no experience. BUT Primavera has many features not included in MSP, which may lead to some differences, e.g. some of the constraints.

How to avoid difference: Switch off the automatic scheduling for MSP. Then the dates will be kept. Hope this will help. If not: Which versions of the software do you use? What are the differences?

Regards

Dieter