Manhrs Loading In P6

Member for

19 years 10 months

Yup i fixed that..Thanks for your help

Member for

18 years 9 months

Hi Praju

This will depend on the duration type.

I assume, that your type is "Fixed duration and units". the a change of budgeted units won’t impact the duration, just units/time.

Regards

Dieter