Oracle Primavera - PM6 Member for 18 years 1 month Member for 18 years 1 month Submitted by K D on Wed, 2008-03-19 04:13 Permalink RE: My Primavera Hi. After changing data in Project management module you have to summarize that project to make data updated in myPrimavera. Regards Member for 23 years 11 months Member for 23 years 11 months Submitted by David Forrest on Tue, 2008-03-18 08:01 Permalink RE: My Primavera Help files are embedded into myPrimavera. If you change anything in P5 then you need to refresh data in myPrimavera, (two circular arrows on top RH side of home screen) Log in or register to post comments
Member for 18 years 1 month Member for 18 years 1 month Submitted by K D on Wed, 2008-03-19 04:13 Permalink RE: My Primavera Hi. After changing data in Project management module you have to summarize that project to make data updated in myPrimavera. Regards
Member for 23 years 11 months Member for 23 years 11 months Submitted by David Forrest on Tue, 2008-03-18 08:01 Permalink RE: My Primavera Help files are embedded into myPrimavera. If you change anything in P5 then you need to refresh data in myPrimavera, (two circular arrows on top RH side of home screen)
Member for
18 years 1 monthRE: My Primavera
Hi.
After changing data in Project management module you have to summarize that project to make data updated in myPrimavera.
Regards
Member for
23 years 11 monthsRE: My Primavera
Help files are embedded into myPrimavera.
If you change anything in P5 then you need to refresh data in myPrimavera, (two circular arrows on top RH side of home screen)