Oracle Primavera - PM6 Member for 18 years 1 month Member for 18 years 1 month Submitted by K D on Wed, 2008-03-19 03:58 Permalink RE: How can I know the target progress in myPrimavera Hi. You also can see baseline bar in Gantt chart. In activity tab -> choose customize view -> in Bar tab, buttom bar choose baseline. Regards Member for 18 years Member for 18 years Submitted by Imran Arshad on Wed, 2008-03-19 03:36 Permalink RE: How can I know the target progress in myPrimavera Dear Niles, In My Primavera P6 follow these steps. 1.open ur project 2.click on work space 3.select customize you will have list of columns from where u can define Basline data date & project baseline columns. Imran Log in or register to post comments
Member for 18 years 1 month Member for 18 years 1 month Submitted by K D on Wed, 2008-03-19 03:58 Permalink RE: How can I know the target progress in myPrimavera Hi. You also can see baseline bar in Gantt chart. In activity tab -> choose customize view -> in Bar tab, buttom bar choose baseline. Regards
Member for 18 years Member for 18 years Submitted by Imran Arshad on Wed, 2008-03-19 03:36 Permalink RE: How can I know the target progress in myPrimavera Dear Niles, In My Primavera P6 follow these steps. 1.open ur project 2.click on work space 3.select customize you will have list of columns from where u can define Basline data date & project baseline columns. Imran
Member for
18 years 1 monthRE: How can I know the target progress in myPrimavera
Hi.
You also can see baseline bar in Gantt chart.
In activity tab -> choose customize view -> in Bar tab, buttom bar choose baseline.
Regards
Member for
18 yearsRE: How can I know the target progress in myPrimavera
Dear Niles,
In My Primavera P6 follow these steps.
1.open ur project
2.click on work space
3.select customize
you will have list of columns from where u can define Basline data date & project baseline columns.
Imran