P5 is using the HOUR as basis of calculation, when P3 is using the DAY !
AS Benjamin said there is not a solution for that. Primavera promized to solve the issue later on as an enhansment request to P6 from the Construction industry !!!
We are still waiting..
Regards
Member for
18 years
Member for18 years1 month
Submitted by Benjamin Mora on Fri, 2008-03-14 12:29
After a lot of discussion with the vendor, the conversion is not always going to be perfect. Allegedly, there things that you can do to the P5 schedule to make the backward conversion better, but I have never seen it done. I think your calendar(s) is this issue.
Member for
18 years 1 monthRE: p5 to p3 conversion date problem
P5 is using the HOUR as basis of calculation, when P3 is using the DAY !
AS Benjamin said there is not a solution for that. Primavera promized to solve the issue later on as an enhansment request to P6 from the Construction industry !!!
We are still waiting..
Regards
Member for
18 yearsRE: p5 to p3 conversion date problem
After a lot of discussion with the vendor, the conversion is not always going to be perfect. Allegedly, there things that you can do to the P5 schedule to make the backward conversion better, but I have never seen it done. I think your calendar(s) is this issue.