p5 to p3 conversion date problem

Member for

18 years 1 month



P5 is using the HOUR as basis of calculation, when P3 is using the DAY !

AS Benjamin said there is not a solution for that. Primavera promized to solve the issue later on as an enhansment request to P6 from the Construction industry !!!

We are still waiting..

Regards

Member for

18 years

After a lot of discussion with the vendor, the conversion is not always going to be perfect. Allegedly, there things that you can do to the P5 schedule to make the backward conversion better, but I have never seen it done. I think your calendar(s) is this issue.