Oracle Primavera - PM6 Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Sat, 2008-01-26 02:41 Permalink RE: Labor Units - Budgeted Vs Planned first of all im not a guru, it is supposed to be the same, however, Budget represents some kind of reality while Planned units could be anything, so I guess it is Budgeted Labor Units that relates to BCWS (but i could be wrong) Log in or register to post comments
Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Sat, 2008-01-26 02:41 Permalink RE: Labor Units - Budgeted Vs Planned first of all im not a guru, it is supposed to be the same, however, Budget represents some kind of reality while Planned units could be anything, so I guess it is Budgeted Labor Units that relates to BCWS (but i could be wrong)
Member for
19 years 1 monthRE: Labor Units - Budgeted Vs Planned
first of all im not a guru, it is supposed to be the same, however, Budget represents some kind of reality while Planned units could be anything, so I guess it is Budgeted Labor Units that relates to BCWS (but i could be wrong)