P6 Template Development

Member for

19 years 3 months

Or, less sophisticated, keep your template projects on a separate branch of the EPS (Enterprise Project Structure), setting their status as "Inactive". Then copy and paste as required.

Member for

24 years 7 months

You need to look at the Methodology Manager which is a separate programme. There is a pdf guide on the installation CD.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au