there is a post in P3 forum where one planner suggests that using multiple holidays calendar be assigned to the activity, but during update it will not be accurate. you try..
Member for
18 years 1 month
Member for18 years2 months
Submitted by Johny Kesserwany on Tue, 2008-01-15 09:46
Not sure about P5 as I can not rememeber but in P6 in the activity form you can use suspend option to break an activity but only for once. It might be the same in P5.
For more breaks, Im afraid you will need to add multiple activities.
In a nutshell, what you can do is create Steps within the activity in question giving weights to each step proportionate to the effort required of the total budget.
Or if you need to divide the activity into discrete parts so that you can either add logic or divide the costs up, you will need to create New seperate tasks and budget them accordingly, (rebasline those activities if your baseline is at that level too)
Member for
18 years 3 monthsRE: How to divide a task in several parts?
there is a post in P3 forum where one planner suggests that using multiple holidays calendar be assigned to the activity, but during update it will not be accurate. you try..
Member for
18 years 1 monthRE: How to divide a task in several parts?
The feature to split task in MSP does not exist in Primavera. You have to go by adding several activities...
JK
Member for
19 yearsRE: How to divide a task in several parts?
Horlen,
Not sure about P5 as I can not rememeber but in P6 in the activity form you can use suspend option to break an activity but only for once. It might be the same in P5.
For more breaks, Im afraid you will need to add multiple activities.
HIH,
Cheers.
Member for
18 years 8 monthsRE: How to divide a task in several parts?
Horlen,
In a nutshell, what you can do is create Steps within the activity in question giving weights to each step proportionate to the effort required of the total budget.
Or if you need to divide the activity into discrete parts so that you can either add logic or divide the costs up, you will need to create New seperate tasks and budget them accordingly, (rebasline those activities if your baseline is at that level too)
My thoughts
Andy