Thanks a lot. I have created 4 different projects for subcontractors. and the Master project for myself with activities mainly of design satge & Control mile stones.I have linked the activities from the respective subcontractor programmes to those mile stones.
*I would like to know whether we can interlink among the sub contractor projects?
*If all the projects are externally linked, then while exporting the files and importing back after feeding the progress the links will remain or we have to link again?
Regards,
Azhar
Member for
18 years 9 months
Member for18 years10 months
Submitted by Dieter Wambach on Sun, 2007-12-09 08:46
You cant export WBS. In your case youll have to create different projects for each subcontractor and one for you - the "master project" and to link them. P6 is working the same way as p5. Each subcontractor can work with his schedule. After import youll do the overall schedule. If youll load them all, Primavera will regard them as just one project. For the later co-operation youll have to decide if youll export the project or EXCEL files for the update.
Be aware of some mines:
- Parameter settings for the database (hours per day..)
- Same data date for all projects before the overall schedule
- Options for import/export (read the help-function first!)
For me this is much easier than in P3.
Regards
Dieter
Member for
18 years 5 months
Member for18 years5 months
Submitted by Mohammed Azharuddin on Sun, 2007-12-09 08:25
Thanks a lot. So In a way I have to make sub Projects under WBS. I have came up with a situation where my project is divided into four sub projects with four different Contractors. I have to give the schedule to each Contractor, and they will be updating their program and will submit it back to me for the preparation of reports.
Can I Export only the WBS related to Contractor-1, and import it back after updating.and the same for other three contractors. Can I again accumulate the date under the same project.
Please could you tell whether it is Possible with P6 or is their any way to tackle such situation.
Regards,
Member for
18 years 5 months
Member for18 years5 months
Submitted by Mohammed Azharuddin on Fri, 2007-12-07 10:05
With P6, you can create or designate any schedule to be a “Master Schedule” with the “sub-schedules” below that using the WBS. Then you need to link the Master Schedule to the others using inter-project logic ties. I know of several large projects that are run this way.
The real problem with this scheme is with updates. When they arrive, you have to start the whole process of creating or designating a new Master Schedule all over again. Schedule Analyzer Software (which I represent) has a module called “Master Switch” that automatically switches the old logic ties from the Master Schedule to the same activities in the new schedules. This is similar to the P3 subproject functionality and perhaps even more flexible.
Member for
18 years 5 monthsRE: Mater project and sub projects in P6
Thanks Oliver.Its complicated but I may get used to it.
Member for
23 yearsRE: Mater project and sub projects in P6
To retain relationships between projects, have a look at the Check Out/Check In functionality
Member for
18 years 1 monthRE: Mater project and sub projects in P6
Hi.
For question 1 : Yes you can create link between many subcontractor projects. Open them all at same time and assign normally.
For question 2 : Ive never checked but I think the link will be intact.
Regards
Member for
18 years 5 monthsRE: Mater project and sub projects in P6
Hi Dieter,
Thanks a lot. I have created 4 different projects for subcontractors. and the Master project for myself with activities mainly of design satge & Control mile stones.I have linked the activities from the respective subcontractor programmes to those mile stones.
*I would like to know whether we can interlink among the sub contractor projects?
*If all the projects are externally linked, then while exporting the files and importing back after feeding the progress the links will remain or we have to link again?
Regards,
Azhar
Member for
18 years 9 monthsRE: Mater project and sub projects in P6
Hi Mohammed
You cant export WBS. In your case youll have to create different projects for each subcontractor and one for you - the "master project" and to link them. P6 is working the same way as p5. Each subcontractor can work with his schedule. After import youll do the overall schedule. If youll load them all, Primavera will regard them as just one project. For the later co-operation youll have to decide if youll export the project or EXCEL files for the update.
Be aware of some mines:
- Parameter settings for the database (hours per day..)
- Same data date for all projects before the overall schedule
- Options for import/export (read the help-function first!)
For me this is much easier than in P3.
Regards
Dieter
Member for
18 years 5 monthsRE: Mater project and sub projects in P6
Hi Ronald,
Thanks a lot. So In a way I have to make sub Projects under WBS. I have came up with a situation where my project is divided into four sub projects with four different Contractors. I have to give the schedule to each Contractor, and they will be updating their program and will submit it back to me for the preparation of reports.
Can I Export only the WBS related to Contractor-1, and import it back after updating.and the same for other three contractors. Can I again accumulate the date under the same project.
Please could you tell whether it is Possible with P6 or is their any way to tackle such situation.
Regards,
Member for
18 years 5 monthsRE: Mater project and sub projects in P6
Hi Kerwany,
Will Portfolio Analysis Help?
Portfolio Analysis is about organizing the projects. I am not aware of Portfolio Analysis.
Regards.
Member for
22 years 10 monthsRE: Mater project and sub projects in P6
With P6, you can create or designate any schedule to be a “Master Schedule” with the “sub-schedules” below that using the WBS. Then you need to link the Master Schedule to the others using inter-project logic ties. I know of several large projects that are run this way.
The real problem with this scheme is with updates. When they arrive, you have to start the whole process of creating or designating a new Master Schedule all over again. Schedule Analyzer Software (which I represent) has a module called “Master Switch” that automatically switches the old logic ties from the Master Schedule to the same activities in the new schedules. This is similar to the P3 subproject functionality and perhaps even more flexible.
Member for
21 years 5 monthsRE: Mater project and sub projects in P6
Thats progress for you!
Member for
18 years 1 monthRE: Mater project and sub projects in P6
Hi Mohammed,
P6 does not support subprojects!!!
and youll find that several helpful functions in P3 are missing in P6!!!
We upgrade and we lose functionnality! amazing no?
Regards
JK