P5 Questions - (Moved to right forum !!)

Member for

19 years

Anoon,



Progress line is no longer available in P5/P6. This was replaced by new screen layout or view that all activities with actual progress will be line up to data date and showing a like split bar when the predecessor of the task is not yet complete depending on the type of relationship used. On this layout you can easily analyse and trace the logic and relationship. Unlike P3x your actual progress bar is crossing over the data date if the predecessor of the task is not yet completed.



Hope this help,

Rodel

Member for

19 years 1 month

Rodel,



Is it possible to show Progress Line in P5/P6 (like in P3)?

I haven’t seen it in P6, I only got progress spotlight.

Member for

19 years

Anoon,



Yes it should be. Please note that it will work only if you have budget units and cost on your resources for more accurate data otherwise you will find that the summary will be not accurate figures.



HTH,

Rodel

Member for

19 years 1 month

Rodel,



Is performance % complete the same as Physical progress? (% type)? Please note, activities physical progress were done manually.



Neil,



Duration type % progress is rolling up automatically in Projects view as well as Activities view. You can input values (% progress) to Level of Effort activities manually.

Member for

18 years 10 months

Worked out how to have it show on the gantt chart as a bar



right click gantt - hit bars

Add a new bar - call it what you need then drop down "timescales" and choose "performance % complete"



Voila !!



Thanks for all your help guys



Neil

Member for

19 years

Neil,



Performance % complete is the same as Activity % complete. If you show both of them in the column you will find it the same. Activity % complete don’t have summary but performance % complete have.



HTH,

Rodel

Member for

18 years 10 months

Rodel



Many thanks ! that solves a problem, however, is there any way that you know of to do this and have a bar that can appear on the gant that shows the rolled up % complete ?



Let me know



Neil

Member for

19 years

Neil,



You can used Performance % Complete as bar label in summary bar. This will summarise your actual progress as long as you have the budget units and budget cost for more accurate figures.



Hope this help,

Rodel

Member for

18 years 10 months

Anoon



Not sure why the activity type would effect the ability to summarise the % complete up to the summary bar.



Perhaps you can expand on this



Cheers



Neil

Member for

19 years 1 month

you got the LOE (Level of Effort) option,..also, i’m not sure, let me check and come back to you later...

Member for

18 years 10 months

Anoon



Thanks for the reply - but I am looking for specifics.



I cannot seem to get it to show Activity % complete at a summary level.



I can see how to show the % complete bar, by going into bars and checking the "show bar when colapsed" in bar settings - however becuase i cannot get any rolled up % complete there is nothing to draw the bar !



I guess my question is now "How do i show the "Activity % complete" at a summary level"



Neil

Member for

19 years 1 month

i think so, just be careful with the settings, specially when you’re using steps (weightings) and manually inputting Physical progress...

Member for

18 years 10 months

Just an addition.



Specifically with regard to summary bars. I can get it to show the summary bar that displays the duration, however what I want is for it to also show the overall % complete bar next to it.



Is this possible ?



Neil