Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2007-10-25 01:03 Permalink RE: Schedule % Complete Hi Richard, Check your resource if Price/Unit = 0 and your Budget Cost = 0. Work Around is to create a WBS Summary Activity for each WBS level and it will show the Schedule % complete total for each Summary. HTH, Rodel Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2007-10-25 01:03 Permalink RE: Schedule % Complete Hi Richard, Check your resource if Price/Unit = 0 and your Budget Cost = 0. Work Around is to create a WBS Summary Activity for each WBS level and it will show the Schedule % complete total for each Summary. HTH, Rodel
Member for
19 yearsRE: Schedule % Complete
Hi Richard,
Check your resource if Price/Unit = 0 and your Budget Cost = 0. Work Around is to create a WBS Summary Activity for each WBS level and it will show the Schedule % complete total for each Summary.
HTH,
Rodel