I spent a week installing my P6 upgrade while a friend of mine spent 60 minutes on overseas telephone support to install his. SQL 2005 Express is no where as forgiving as MSDE was. Good luck!
Member for
18 years 9 months
Member for18 years10 months
Submitted by Dieter Wambach on Wed, 2007-09-05 05:37
Move the mouse into the bar chart --> click right button --> Bars --> Select bar "Summary" - the one whose filter is "summary" --> select "Bar Labels" --> select the data item you dont want to be displayed --> "Delete"
Member for
18 years 9 monthsRE: P5 Summary Dates
Thank you Ronald
Installation will be Sep 11. We need some of the enhancements. Therefore well install so early. In general I prefer to wait for the first patch.
Regards
Dieter
Member for
22 years 10 monthsRE: P5 Summary Dates
Dieter,
I concur with your PAR; they should do the install. Refer to http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=37287 for hardware requirements. Only computers with XP Professional or Vista Professional will qualify for the stand-alone upgrade.
I spent a week installing my P6 upgrade while a friend of mine spent 60 minutes on overseas telephone support to install his. SQL 2005 Express is no where as forgiving as MSDE was. Good luck!
Member for
18 years 9 monthsRE: P5 Summary Dates
Hi Susan
We were informed, that during this month it will be delievered to customers.
Our PAR informed us, that this time well better let them install the upgrade.
Regards
Dieter
Member for
22 years 8 monthsRE: P5 Summary Dates
Thanks for the inputs.
Does anybody know when P6 will be released ? I notice that even Progress Line function is absent in P5 !
S
Member for
20 years 6 monthsRE: P5 Summary Dates
I print to PDF and then use Acrobat to delete the boxes of text for Start, Finish, % and total Float in the summary bars.
Member for
19 years 11 monthsRE: P5 Summary Dates
Hi Susan,
I also experienced the same with you...
The last thing I did just for presentation purposes...
1. Create User Define Field - Start
2. Global Change : Start = Start
3. View the UDF on activity table
It did gave a date on activities without summary dates...
Hope it helps.
Arman
Member for
18 years 9 monthsRE: P5 Summary Dates
Hi Susan
This is announced for P6.
Regards
Dieter
Member for
22 years 8 monthsRE: P5 Summary Dates
Thanks a lot Dieter,
I tried it already !
What I want is to remove the summarized dates from the Start & Finish Columns (Activity Table).
Any suggestions ?
Thanks
Susan
Member for
18 years 9 monthsRE: P5 Summary Dates
Hi Susan
Move the mouse into the bar chart --> click right button --> Bars --> Select bar "Summary" - the one whose filter is "summary" --> select "Bar Labels" --> select the data item you dont want to be displayed --> "Delete"
Good luck
Dieter