The reason for this conversion is because while P3 planning base was daily, P5 is hourly.
Therefore as default any resource without unit declared in P3 will be multiplied by 8.
But this situation can be solved if you enter a resource unit in the resources window, then if you state a unit like h, hr, etc P5 during normla importation will consider that these resources are already in a hourly base and will not multiply.
This is the best solution that I can give you at this moment. I am checking the posibility to consider blank units as hourly units through modifiying the PrmConvert.ini file. If a get something I will post it here.
Member for
22 years 9 monthsRE: Converted Data P3x to P5 _ Not correct
another easy solution
run a global change to
OD = OD /8
BQ = BQ /8
if that is the only different
Alex
Member for
22 yearsRE: Converted Data P3x to P5 _ Not correct
Hello,
The reason for this conversion is because while P3 planning base was daily, P5 is hourly.
Therefore as default any resource without unit declared in P3 will be multiplied by 8.
But this situation can be solved if you enter a resource unit in the resources window, then if you state a unit like h, hr, etc P5 during normla importation will consider that these resources are already in a hourly base and will not multiply.
This is the best solution that I can give you at this moment. I am checking the posibility to consider blank units as hourly units through modifiying the PrmConvert.ini file. If a get something I will post it here.
Regards
Miguel