Oracle Primavera - PM6 Member for 18 years 9 months Member for 18 years 10 months Submitted by Dieter Wambach on Wed, 2007-06-13 09:58 Permalink RE: Importing from P3 to P5 Hi Dev There is aparameter in the import procedure. If you select "Combine subproject" the activity codes will be imported as project activity codes. Otherwise as global. Regards Dieter Log in or register to post comments
Member for 18 years 9 months Member for 18 years 10 months Submitted by Dieter Wambach on Wed, 2007-06-13 09:58 Permalink RE: Importing from P3 to P5 Hi Dev There is aparameter in the import procedure. If you select "Combine subproject" the activity codes will be imported as project activity codes. Otherwise as global. Regards Dieter
Member for
18 years 9 monthsRE: Importing from P3 to P5
Hi Dev
There is aparameter in the import procedure. If you select "Combine subproject" the activity codes will be imported as project activity codes. Otherwise as global.
Regards
Dieter