Then it is very simple, press Shift F7 and the resource table will appear right at the bottom. Select the time scale and Peak under diplay tab of the table.
I think you are looking for something similar to what the Peak function of P3 did in Reoruce Table. I am also a fan of that and was very upset when it was not found in P3e/c.
Somewhat similar results can be obtained via Spread Options in Resource Spreadsheet. This can be accessed by cliking on Display on rightmost window of Resource Spreadsheet.
In P3e there is no "Spreadsheet Options". What it has is only Spreadsheet Fields which contains only options which are predetermined and we cannot apply any formula to them. Can you please elaborate if I am still at mistake?
you can divide the spreadsheet by right-clicking and chosing "Spreadsheet options" to divide the values by a constant. (intutitive or what!)
Note that this constant CANNOT be based on the hours per day that the resource works, just the number you give it, or the current hours-per day/week in the admin or user preferences. There is no equivalent of P3 3.1s "Peak" setting
Member for
20 years 6 monthsRE: Men/day in Resource Spreadsheet of P3e version
Sorry about the mistake, i have used P3e/c 4.0 and 5.0 and have no clue about the version which you are using.
Regards
Rashid
Member for
19 years 4 monthsRE: Men/day in Resource Spreadsheet of P3e version
Hi Rashid,
You are right in your saying. But this is true for P3 ver 3.1, while the version which I have is P3e 3.5.1, which is not the same.
Member for
20 years 6 monthsRE: Men/day in Resource Spreadsheet of P3e version
Then it is very simple, press Shift F7 and the resource table will appear right at the bottom. Select the time scale and Peak under diplay tab of the table.
Let me know if thre is still any problem.
Regards
Rashid
Member for
19 years 4 monthsRE: Men/day in Resource Spreadsheet of P3e version
Thanks Rashid but I dont have P3e/c. My version is old one (P3e 3.5.1) which does not contain "Spread Options" option.
Member for
20 years 6 monthsRE: Men/day in Resource Spreadsheet of P3e version
Ijaz,
I think you are looking for something similar to what the Peak function of P3 did in Reoruce Table. I am also a fan of that and was very upset when it was not found in P3e/c.
Somewhat similar results can be obtained via Spread Options in Resource Spreadsheet. This can be accessed by cliking on Display on rightmost window of Resource Spreadsheet.
Regards
Rashid
Member for
19 years 4 monthsRE: Men/day in Resource Spreadsheet of P3e version
I have version 3.5.1 of P3e
Member for
21 yearsRE: Men/day in Resource Spreadsheet of P3e version
Which version of P3e do you have? Its listed under the help pull down
Member for
19 years 4 monthsRE: Men/day in Resource Spreadsheet of P3e version
In P3e there is no "Spreadsheet Options". What it has is only Spreadsheet Fields which contains only options which are predetermined and we cannot apply any formula to them. Can you please elaborate if I am still at mistake?
Member for
21 yearsRE: Men/day in Resource Spreadsheet of P3e version
you can divide the spreadsheet by right-clicking and chosing "Spreadsheet options" to divide the values by a constant. (intutitive or what!)
Note that this constant CANNOT be based on the hours per day that the resource works, just the number you give it, or the current hours-per day/week in the admin or user preferences. There is no equivalent of P3 3.1s "Peak" setting