Of couse there is, unless you are using a very old version. At the Admin Preferneces Time periods you can select to use the assigned calendar for hours-per-day figures,
BUT
If the group-and-sort band contains activities with more than one calendar, then the default calendars hours-per-day figue is used.
Member for
14 years 2 monthsThanks Dave.For some reason,
Thanks Dave.
For some reason, even when the option to use the assigned calendar is ticked, the variance is not what it should be.
But having the option to define the hours/day, etc allowed me to get to a number that is closer to what it is supposed to be.
Member for
9 years 8 monthsOf couse there is, unless you
Of couse there is, unless you are using a very old version. At the Admin Preferneces Time periods you can select to use the assigned calendar for hours-per-day figures,
BUT
If the group-and-sort band contains activities with more than one calendar, then the default calendars hours-per-day figue is used.