The 1st part of the 2 words is Approved so it is officially Approved but you are expected to incorporate the "AS|NOTED" part in your next submittal. As far as the 2 weeks vs 4 weeks durations if it is YOUR activity then they can not dictate the duration. If it ia an owner activity then they can comment and say this will only take them 2 weeks instead of 4 weeks. Activities that are installation activities usually have a quantity to install. Then depending on the number of men doing the installation determines the duration. So the 4 week duration may represent 2 men working for 4 weeks or you can use 4 men working for 2 weeks. Thsi can not be dictated by the owner and is part of the means and methods.
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Fri, 2021-08-27 11:46
"Approved as Noted" means it is approved providing you complied on the notes (which usually minor issues that would not stop from using it with the guidance or subject to complied on the notes stated). Yes, you can use that as a baseline subject to complied on the notes stated. It will not be approved if a major issues has been found and will returned as "revised and re-submit" instead.
Member for
16 years 3 monthsThe 1st part of the 2 words
The 1st part of the 2 words is Approved so it is officially Approved but you are expected to incorporate the "AS|NOTED" part in your next submittal. As far as the 2 weeks vs 4 weeks durations if it is YOUR activity then they can not dictate the duration. If it ia an owner activity then they can comment and say this will only take them 2 weeks instead of 4 weeks. Activities that are installation activities usually have a quantity to install. Then depending on the number of men doing the installation determines the duration. So the 4 week duration may represent 2 men working for 4 weeks or you can use 4 men working for 2 weeks. Thsi can not be dictated by the owner and is part of the means and methods.
Member for
19 years"Approved as Noted" means it
"Approved as Noted" means it is approved providing you complied on the notes (which usually minor issues that would not stop from using it with the guidance or subject to complied on the notes stated). Yes, you can use that as a baseline subject to complied on the notes stated. It will not be approved if a major issues has been found and will returned as "revised and re-submit" instead.