Overall Weightage by Cost

Member for

16 years 3 months

yes it will roll up 

Member for

14 years 7 months

Thanks Zoltan,

 

So by this each WBS would have its own weightage and overall WBS would show the total progress Planned and Actual ?

 

Regards

Jithin

Member for

16 years 3 months

1st go to the PROJECTS directory 

make sure that your project is open 

click on the reources tab and at the bottom make sure that resources can be assigned to teh same activity more than once is NOT checked

go to activites now go to Resources and on the rigth select add

create an new resource call it lumpsum make sure that calculate cost from units is NOT checked

filter for all of the activites thet you want cost on 

select all activities

right click

assign resource select LUMP sum

select file export and export the resource and cost to excel

populate cost values in excel for each actviity 

save file 

import back into p6

view show on bottom resource useage profile 

done