Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2019-11-20 14:51 Permalink yes it will roll up yes it will roll up Member for 14 years 7 months Member for 14 years 7 months Submitted by jithin on Wed, 2019-11-20 11:40 Permalink Thanks Zoltan, So by this Thanks Zoltan, So by this each WBS would have its own weightage and overall WBS would show the total progress Planned and Actual ? Regards Jithin Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2019-11-18 14:28 Permalink 1st go to the PROJECTS 1st go to the PROJECTS directory make sure that your project is open click on the reources tab and at the bottom make sure that resources can be assigned to teh same activity more than once is NOT checked go to activites now go to Resources and on the rigth select add create an new resource call it lumpsum make sure that calculate cost from units is NOT checked filter for all of the activites thet you want cost on select all activities right click assign resource select LUMP sum select file export and export the resource and cost to excel populate cost values in excel for each actviity save file import back into p6 view show on bottom resource useage profile done Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2019-11-20 14:51 Permalink yes it will roll up yes it will roll up
Member for 14 years 7 months Member for 14 years 7 months Submitted by jithin on Wed, 2019-11-20 11:40 Permalink Thanks Zoltan, So by this Thanks Zoltan, So by this each WBS would have its own weightage and overall WBS would show the total progress Planned and Actual ? Regards Jithin
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2019-11-18 14:28 Permalink 1st go to the PROJECTS 1st go to the PROJECTS directory make sure that your project is open click on the reources tab and at the bottom make sure that resources can be assigned to teh same activity more than once is NOT checked go to activites now go to Resources and on the rigth select add create an new resource call it lumpsum make sure that calculate cost from units is NOT checked filter for all of the activites thet you want cost on select all activities right click assign resource select LUMP sum select file export and export the resource and cost to excel populate cost values in excel for each actviity save file import back into p6 view show on bottom resource useage profile done
Member for
16 years 3 monthsyes it will roll up
yes it will roll up
Member for
14 years 7 monthsThanks Zoltan, So by this
Thanks Zoltan,
So by this each WBS would have its own weightage and overall WBS would show the total progress Planned and Actual ?
Regards
Jithin
Member for
16 years 3 months1st go to the PROJECTS
1st go to the PROJECTS directory
make sure that your project is open
click on the reources tab and at the bottom make sure that resources can be assigned to teh same activity more than once is NOT checked
go to activites now go to Resources and on the rigth select add
create an new resource call it lumpsum make sure that calculate cost from units is NOT checked
filter for all of the activites thet you want cost on
select all activities
right click
assign resource select LUMP sum
select file export and export the resource and cost to excel
populate cost values in excel for each actviity
save file
import back into p6
view show on bottom resource useage profile
done