Problem with importing resources in P6

Member for

16 years 3 months

make sure that durgin the import process thet you select modify then for the resource select insert new

Member for

6 years 3 months

yes..its done.but still the same issue

Member for

16 years 3 months

make sure that calculate cost from units is NOT checked. Also at the project level under the resource tab make sure that Resources can be assigned to the same activity more than once is NOT checked