Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2019-07-18 14:18 Permalink make sure that durgin the make sure that durgin the import process thet you select modify then for the resource select insert new Member for 6 years 3 months Member for 6 years 3 months Submitted by prince89 on Thu, 2019-07-18 08:11 Permalink yes..its done.but still the yes..its done.but still the same issue Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2019-07-17 14:08 Permalink make sure that calculate cost make sure that calculate cost from units is NOT checked. Also at the project level under the resource tab make sure that Resources can be assigned to the same activity more than once is NOT checked Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2019-07-18 14:18 Permalink make sure that durgin the make sure that durgin the import process thet you select modify then for the resource select insert new
Member for 6 years 3 months Member for 6 years 3 months Submitted by prince89 on Thu, 2019-07-18 08:11 Permalink yes..its done.but still the yes..its done.but still the same issue
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2019-07-17 14:08 Permalink make sure that calculate cost make sure that calculate cost from units is NOT checked. Also at the project level under the resource tab make sure that Resources can be assigned to the same activity more than once is NOT checked
Member for
16 years 3 monthsmake sure that durgin the
make sure that durgin the import process thet you select modify then for the resource select insert new
Member for
6 years 3 monthsyes..its done.but still the
yes..its done.but still the same issue
Member for
16 years 3 monthsmake sure that calculate cost
make sure that calculate cost from units is NOT checked. Also at the project level under the resource tab make sure that Resources can be assigned to the same activity more than once is NOT checked