Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2018-10-26 19:03 Permalink you stays will tell you that you stays will tell you that based on where you should be and where you actually are Member for 7 years 6 months Member for 7 years 6 months Submitted by Kathy Castle on Fri, 2018-10-26 16:19 Permalink Are you asking techniques Are you asking techniques related with construction delay analysis ? Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2018-10-22 15:20 Permalink the delay is when it was the delay is when it was originally planned to finish - when it is forecated to finish original completion date December 15, 2018 current completion date Jnauary 15, 2019 Delay - 31 calendar days Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2018-10-26 19:03 Permalink you stays will tell you that you stays will tell you that based on where you should be and where you actually are
Member for 7 years 6 months Member for 7 years 6 months Submitted by Kathy Castle on Fri, 2018-10-26 16:19 Permalink Are you asking techniques Are you asking techniques related with construction delay analysis ?
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2018-10-22 15:20 Permalink the delay is when it was the delay is when it was originally planned to finish - when it is forecated to finish original completion date December 15, 2018 current completion date Jnauary 15, 2019 Delay - 31 calendar days
Member for
16 years 3 monthsyou stays will tell you that
you stays will tell you that based on where you should be and where you actually are
Member for
7 years 6 monthsAre you asking techniques
Are you asking techniques related with construction delay analysis ?
Member for
16 years 3 monthsthe delay is when it was
the delay is when it was originally planned to finish - when it is forecated to finish
original completion date December 15, 2018
current completion date Jnauary 15, 2019
Delay - 31 calendar days