How do you show 3 baselines on one bar?

Member for

16 years 3 months

glad I could help 

Member for

9 years 7 months

Worked it out. Filter the bars by PS and CD 

Member for

9 years 7 months

[[wysiwyg_imageupload:6193:]]

Member for

9 years 7 months

Thank you
In poorly explaining it.
I know I need to filter the bars....so you can only see the delay

Member for

16 years 3 months

then put them all on the same row number. this is not the correct way to do it but its your call i am just telling you how to do what you want.

Member for

9 years 7 months

Cheers. Oh. The picture isn't there...

I do want them overlapped

I want one bar that goes up to a point with the baseline date, then goes further with the update and to the end with the last update (poorly explained I know)

Member for

16 years 3 months

1st maintain and assign 3 baselines 

then in the gantt area right click bars and select the primary baseline, the seconday basline and the tertiary basline  

make sure that each of these has their own row number (listed under Pattern) or they may be on top of one another.