Retaining Activity ID logic

Member for

16 years 3 months

that certainly would help to have the database in a centralized location

Member for

9 years 8 months

Thank you. I thought I would ask the question and I think the only way forward is to use a single database that external parties have access to, such as a Loadspring. As each file is external and issued from and external source the Project ID differs each issue. I was not sure if there was a new way of tackliing this. Cheers

Member for

16 years 3 months

why dont you just continue to use the same schedule this way the project id and activit ids stay the same. Whne you are done with you update copy that project and save it as the update for the month or period. Then you have your historical schedule data if you need it.