Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2018-01-03 13:36 Permalink just make sure that you set a just make sure that you set a defaul calendar for the PROJECT Member for 14 years 7 months Member for 14 years 7 months Submitted by jithin on Wed, 2018-01-03 09:58 Permalink HI Everyone, Got the Answer HI Everyone, Got the Answer after doing some research, I went to Enterprise - Calendars - Global Section - Then I moved Default Calandar Tick from the Calendar which had a 5 Day Work week to 7 Day Work Week. Now the Total Duration is same as the the Below WBS Duration. Regards Jithin Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2018-01-03 13:36 Permalink just make sure that you set a just make sure that you set a defaul calendar for the PROJECT
Member for 14 years 7 months Member for 14 years 7 months Submitted by jithin on Wed, 2018-01-03 09:58 Permalink HI Everyone, Got the Answer HI Everyone, Got the Answer after doing some research, I went to Enterprise - Calendars - Global Section - Then I moved Default Calandar Tick from the Calendar which had a 5 Day Work week to 7 Day Work Week. Now the Total Duration is same as the the Below WBS Duration. Regards Jithin
Member for
16 years 3 monthsjust make sure that you set a
just make sure that you set a defaul calendar for the PROJECT
Member for
14 years 7 monthsHI Everyone, Got the Answer
HI Everyone,
Got the Answer after doing some research,
I went to Enterprise - Calendars - Global Section - Then I moved Default Calandar Tick from the Calendar which had a 5 Day Work week to 7 Day Work Week.
Now the Total Duration is same as the the Below WBS Duration.
Regards
Jithin