Duration Difference - At Completion Duration based on Default Calendar

Member for

16 years 3 months

just make sure that you set a defaul calendar for the PROJECT

Member for

14 years 7 months

HI Everyone,

 

Got the Answer after doing some research,

 

I went to Enterprise - Calendars - Global Section - Then I moved Default Calandar Tick from the Calendar which had a 5 Day Work week to 7 Day Work Week.

Now the Total Duration is same as the the Below WBS Duration.

 

Regards

Jithin