Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2017-04-07 13:45 Permalink what is your Resource what is your Resource assigment setting in the Projects directory ? add actual to remaining or subtract actual from at completion ? also do you have Recalculate Actual Units and costs when duration % changes ? Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2017-04-07 13:45 Permalink what is your Resource what is your Resource assigment setting in the Projects directory ? add actual to remaining or subtract actual from at completion ? also do you have Recalculate Actual Units and costs when duration % changes ?
Member for
16 years 3 monthswhat is your Resource
what is your Resource assigment setting in the Projects directory ?
add actual to remaining or subtract actual from at completion ?
also do you have Recalculate Actual Units and costs when duration % changes ?