Planning, Scheduling & Programming Discussion Member for 24 years 9 months Member for 24 years 9 months Submitted by Patrick Weaver on Sat, 2017-03-18 10:25 Permalink Float is the least of your Float is the least of your worries - first make sure the logic, resources, and durations are accurate, reasonable and achievable. Float is simply a by-product, see: http://www.mosaicprojects.com.au/PDF/Schedule_Float.pdf Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2017-03-08 11:10 Permalink Hi OgutandeTighten up the Hi Ogutande Tighten up the logic by removing loose ends. Adjust all SS FF Links - best to use only FS logic. Remove all constraints. Best regards Mike T. Log in or register to post comments
Member for 24 years 9 months Member for 24 years 9 months Submitted by Patrick Weaver on Sat, 2017-03-18 10:25 Permalink Float is the least of your Float is the least of your worries - first make sure the logic, resources, and durations are accurate, reasonable and achievable. Float is simply a by-product, see: http://www.mosaicprojects.com.au/PDF/Schedule_Float.pdf
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2017-03-08 11:10 Permalink Hi OgutandeTighten up the Hi Ogutande Tighten up the logic by removing loose ends. Adjust all SS FF Links - best to use only FS logic. Remove all constraints. Best regards Mike T.
Member for
24 years 9 monthsFloat is the least of your
Float is the least of your worries - first make sure the logic, resources, and durations are accurate, reasonable and achievable. Float is simply a by-product, see: http://www.mosaicprojects.com.au/PDF/Schedule_Float.pdf
Member for
19 years 10 monthsHi OgutandeTighten up the
Hi Ogutande
Tighten up the logic by removing loose ends.
Adjust all SS FF Links - best to use only FS logic.
Remove all constraints.
Best regards