Planning, Scheduling & Programming Discussion Member for 9 years 8 months Member for 9 years 9 months Submitted by Philip34 on Tue, 2016-12-13 16:10 Permalink Thank you. Just need to work Thank you. Just need to work out how to do that. I've never used resources in P6 Bit of trial and error :-) Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2016-12-13 15:23 Permalink Hi PhilipIn most programmes Hi Philip In most programmes you can put in a resource levelling system on your deliverable resource - allowing only 2 per week. Best regards Mike Testro Log in or register to post comments
Member for 9 years 8 months Member for 9 years 9 months Submitted by Philip34 on Tue, 2016-12-13 16:10 Permalink Thank you. Just need to work Thank you. Just need to work out how to do that. I've never used resources in P6 Bit of trial and error :-)
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2016-12-13 15:23 Permalink Hi PhilipIn most programmes Hi Philip In most programmes you can put in a resource levelling system on your deliverable resource - allowing only 2 per week. Best regards Mike Testro
Member for
9 years 8 monthsThank you. Just need to work
Thank you. Just need to work out how to do that. I've never used resources in P6
Bit of trial and error :-)
Member for
19 years 10 monthsHi PhilipIn most programmes
Hi Philip
In most programmes you can put in a resource levelling system on your deliverable resource - allowing only 2 per week.
Best regards
Mike Testro