Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2016-11-06 11:53 Permalink Hi AntonyProduction of Hi Antony Production of earthworks is controlled by the disposal rate of the excavated material. This is calculated by the volume of the haul units and the distance travelled - controlled by the capacity of the haul roads. Once that has been established the excavating kit can be set from the manufacturers catalogues - set at 120% of the disposal rate. The digger can wait a bit but the disposal must be non stop. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2016-11-06 11:53 Permalink Hi AntonyProduction of Hi Antony Production of earthworks is controlled by the disposal rate of the excavated material. This is calculated by the volume of the haul units and the distance travelled - controlled by the capacity of the haul roads. Once that has been established the excavating kit can be set from the manufacturers catalogues - set at 120% of the disposal rate. The digger can wait a bit but the disposal must be non stop. Best regards Mike Testro
Member for
19 years 10 monthsHi AntonyProduction of
Hi Antony
Production of earthworks is controlled by the disposal rate of the excavated material.
This is calculated by the volume of the haul units and the distance travelled - controlled by the capacity of the haul roads.
Once that has been established the excavating kit can be set from the manufacturers catalogues - set at 120% of the disposal rate.
The digger can wait a bit but the disposal must be non stop.
Best regards
Mike Testro