The single most important purpose of a construction plan is "does it respond dynsmically to change".

Therefore the things to check - particularly in P6 are.

1. Negative Float - indicates an obstruction in the logic - check the imposed end date.

2. Constriants - Remove them all and reschedule to get the true end date.

3. Calendars - check the non working days and work patterns

4. Logic - at level 3 these will all be SS or FF with lead lags - check to see how realistic they are by doing a Level 4 sub chart.

5. Check for open end logic - try a dummy progress update where the date is beyond the SS lag and reschedule - see what it does for the end date.

I hope that helps a bit - good luck with your new career.

Best regards

Mike Testro