Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2016-09-15 11:01 Permalink Hi PhilipThe single most Hi Philip The single most important purpose of a construction plan is "does it respond dynsmically to change". Therefore the things to check - particularly in P6 are. 1. Negative Float - indicates an obstruction in the logic - check the imposed end date. 2. Constriants - Remove them all and reschedule to get the true end date. 3. Calendars - check the non working days and work patterns 4. Logic - at level 3 these will all be SS or FF with lead lags - check to see how realistic they are by doing a Level 4 sub chart. 5. Check for open end logic - try a dummy progress update where the date is beyond the SS lag and reschedule - see what it does for the end date. I hope that helps a bit - good luck with your new career. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2016-09-15 11:01 Permalink Hi PhilipThe single most Hi Philip The single most important purpose of a construction plan is "does it respond dynsmically to change". Therefore the things to check - particularly in P6 are. 1. Negative Float - indicates an obstruction in the logic - check the imposed end date. 2. Constriants - Remove them all and reschedule to get the true end date. 3. Calendars - check the non working days and work patterns 4. Logic - at level 3 these will all be SS or FF with lead lags - check to see how realistic they are by doing a Level 4 sub chart. 5. Check for open end logic - try a dummy progress update where the date is beyond the SS lag and reschedule - see what it does for the end date. I hope that helps a bit - good luck with your new career. Best regards Mike Testro
Member for
19 years 10 monthsHi PhilipThe single most
Hi Philip
The single most important purpose of a construction plan is "does it respond dynsmically to change".
Therefore the things to check - particularly in P6 are.
1. Negative Float - indicates an obstruction in the logic - check the imposed end date.
2. Constriants - Remove them all and reschedule to get the true end date.
3. Calendars - check the non working days and work patterns
4. Logic - at level 3 these will all be SS or FF with lead lags - check to see how realistic they are by doing a Level 4 sub chart.
5. Check for open end logic - try a dummy progress update where the date is beyond the SS lag and reschedule - see what it does for the end date.
I hope that helps a bit - good luck with your new career.