Actual Units Update Issue

Member for

9 years

I am using P6.

When I update the progress in my activity and manually insert the actual units, when I schedule the plan, the actuals units overwrite.

 

Thanks

Member for

8 years 7 months

Friends,

i m also feeling the same problem 

 

Thanks.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Member for

16 years 3 months

what software  ?

Member for

9 years

Hi John,

 

Have you been able to find the answer to this question. I have the same problem. I have tried to change different settings, but I don't seem to find the correct one.

 

Thanks