Planning, Scheduling & Programming Discussion Member for 9 years Member for 9 years Submitted by GemaLA on Sun, 2017-03-12 20:33 Permalink I am using P6.When I update I am using P6. When I update the progress in my activity and manually insert the actual units, when I schedule the plan, the actuals units overwrite. Thanks Member for 8 years 7 months Member for 8 years 8 months Submitted by pr*****@g***** on Sat, 2017-03-11 09:49 Permalink Friends,i m also feeling the Friends, i m also feeling the same problem Thanks. Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2017-03-09 13:48 Permalink what software ? what software ? Member for 9 years Member for 9 years Submitted by GemaLA on Thu, 2017-03-09 13:21 Permalink Hi John, Have you been able Hi John, Have you been able to find the answer to this question. I have the same problem. I have tried to change different settings, but I don't seem to find the correct one. Thanks Log in or register to post comments
Member for 9 years Member for 9 years Submitted by GemaLA on Sun, 2017-03-12 20:33 Permalink I am using P6.When I update I am using P6. When I update the progress in my activity and manually insert the actual units, when I schedule the plan, the actuals units overwrite. Thanks
Member for 8 years 7 months Member for 8 years 8 months Submitted by pr*****@g***** on Sat, 2017-03-11 09:49 Permalink Friends,i m also feeling the Friends, i m also feeling the same problem Thanks.
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2017-03-09 13:48 Permalink what software ? what software ?
Member for 9 years Member for 9 years Submitted by GemaLA on Thu, 2017-03-09 13:21 Permalink Hi John, Have you been able Hi John, Have you been able to find the answer to this question. I have the same problem. I have tried to change different settings, but I don't seem to find the correct one. Thanks
Member for
9 yearsI am using P6.When I update
I am using P6.
When I update the progress in my activity and manually insert the actual units, when I schedule the plan, the actuals units overwrite.
Thanks
Member for
8 years 7 monthsFriends,i m also feeling the
Friends,
i m also feeling the same problem
Thanks.
Member for
16 years 3 monthswhat software ?
what software ?
Member for
9 yearsHi John, Have you been able
Hi John,
Have you been able to find the answer to this question. I have the same problem. I have tried to change different settings, but I don't seem to find the correct one.
Thanks