Revised Planned Percentage

Member for

15 years 11 months

You are Welcome Jithin...

Member for

14 years 7 months

Thanks Ray,

Thats the answer i was looking for and the same thing is what i followed from the start. I just needed a confirmation of what i did was correct. Thank you very much.  

Member for

15 years 11 months

Hi,

You can only change when there is instruction from the Client to submit a Revised Baseline Schedule due to Changes & Modifications.

Regards,

Member for

14 years 7 months

Thanks Ray,

But can you change the Planned % without clients approval from the first planned % which was submitted (S curve) and approved by client. Are we (Contractor) authorised to change the planned % without clients approval.

 

ItemBaseline Planned %Actual Completed %Engineering  Procurement  Construction  

Thanks

JK

Member for

15 years 11 months

HI,

The Contractor is solely in Control of the Program such as the Activities sequencing, Costs, durations, etc, therefore the Planned % shall be according to Contractors ability to execute the Schedule.

 

Regards,