Planning, Scheduling & Programming Discussion Member for 21 years 10 months Member for 21 years 10 months Submitted by moutaz aldeib on Sat, 2015-03-28 14:30 Permalink Thanks Ahmed and Thanks Ahmed and Mike Best, Moutaz Member for 14 years 11 months Member for 15 years Submitted by akherief on Sat, 2015-03-28 10:11 Permalink We revise a programme in case We revise a programme in case of EOT, scope change (addition or deletion), Quantities changes Recovery plan is the way to absorbe the delay and turn back to the original project finish date. Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2015-03-27 17:24 Permalink Hi MoutazYou prepare a Hi Moutaz You prepare a recovery plan to try to reduce a delay situation. You revise a plan if there is a different way of doing things. Best regards Mike Testro Log in or register to post comments
Member for 21 years 10 months Member for 21 years 10 months Submitted by moutaz aldeib on Sat, 2015-03-28 14:30 Permalink Thanks Ahmed and Thanks Ahmed and Mike Best, Moutaz
Member for 14 years 11 months Member for 15 years Submitted by akherief on Sat, 2015-03-28 10:11 Permalink We revise a programme in case We revise a programme in case of EOT, scope change (addition or deletion), Quantities changes Recovery plan is the way to absorbe the delay and turn back to the original project finish date.
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2015-03-27 17:24 Permalink Hi MoutazYou prepare a Hi Moutaz You prepare a recovery plan to try to reduce a delay situation. You revise a plan if there is a different way of doing things. Best regards Mike Testro
Member for
21 years 10 monthsThanks Ahmed and
Thanks Ahmed and Mike
Best,
Moutaz
Member for
14 years 11 monthsWe revise a programme in case
We revise a programme in case of EOT, scope change (addition or deletion), Quantities changes
Recovery plan is the way to absorbe the delay and turn back to the original project finish date.
Member for
19 years 10 monthsHi MoutazYou prepare a
Hi Moutaz
You prepare a recovery plan to try to reduce a delay situation.
You revise a plan if there is a different way of doing things.
Best regards
Mike Testro