Actual Units for Assigned Resources are not correct as per physical %

Member for

16 years 3 months

since you are using physical % complete the duration % complete never gets updated so you need to run a global change to set the duration % complete equal to the physical % complete 

first check this setting 

go to the projects directory make sure that your project is highlighted click on the calculations tab and make sure that on the right that Recalculate actual units and cost when duration % complete changes is checked

now run the global change

go to tools global change

select new

where physical % complete is greater than 0

then duration % complete eqauls physical % complete