since you are using physical % complete the duration % complete never gets updated so you need to run a global change to set the duration % complete equal to the physical % complete
first check this setting
go to the projects directory make sure that your project is highlighted click on the calculations tab and make sure that on the right that Recalculate actual units and cost when duration % complete changes is checked
now run the global change
go to tools global change
select new
where physical % complete is greater than 0
then duration % complete eqauls physical % complete
Member for
16 years 3 monthssince you are using physical
since you are using physical % complete the duration % complete never gets updated so you need to run a global change to set the duration % complete equal to the physical % complete
first check this setting
go to the projects directory make sure that your project is highlighted click on the calculations tab and make sure that on the right that Recalculate actual units and cost when duration % complete changes is checked
now run the global change
go to tools global change
select new
where physical % complete is greater than 0
then duration % complete eqauls physical % complete