Planning, Scheduling & Programming Discussion Member for 18 years 6 months Member for 18 years 6 months Submitted by shahid nazir on Thu, 2015-03-05 06:54 Permalink Need to change order in " Need to change order in " format bars". 2nd option: use a layout from builtin layouts which shows critical rollup activities on top and adjust as you need. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2015-02-13 12:55 Permalink sort by total float sort by total float Member for 12 years 9 months Member for 12 years 9 months Submitted by phayward on Fri, 2015-02-13 12:45 Permalink but i need to show both but i need to show both critical and non-critical activities. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2015-02-10 13:34 Permalink filter for critical filter for critical activities only Log in or register to post comments
Member for 18 years 6 months Member for 18 years 6 months Submitted by shahid nazir on Thu, 2015-03-05 06:54 Permalink Need to change order in " Need to change order in " format bars". 2nd option: use a layout from builtin layouts which shows critical rollup activities on top and adjust as you need.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2015-02-13 12:55 Permalink sort by total float sort by total float
Member for 12 years 9 months Member for 12 years 9 months Submitted by phayward on Fri, 2015-02-13 12:45 Permalink but i need to show both but i need to show both critical and non-critical activities.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2015-02-10 13:34 Permalink filter for critical filter for critical activities only
Member for
18 years 6 monthsNeed to change order in "
Need to change order in " format bars".
2nd option: use a layout from builtin layouts which shows critical rollup activities on top and adjust as you need.
Member for
16 years 3 monthssort by total float
sort by total float
Member for
12 years 9 monthsbut i need to show both
but i need to show both critical and non-critical activities.
Member for
16 years 3 monthsfilter for critical
filter for critical activities only