Planning, Scheduling & Programming Discussion Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Tue, 2014-12-16 19:08 Permalink Suggest to check the Percent Suggest to check the Percent Type of Activities. It must be Physical. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2014-12-16 13:42 Permalink where did you get the excel where did you get the excel file that you are importing ? create an excel file to populate with your updated information by exporting the fields that you want this give you a template. also go to the project mode big button on the left and make sure that you projetc is highlighted click on the calculations tab on the left make sure that Activity Percent complete based on activity steps is NOT checked Log in or register to post comments
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Tue, 2014-12-16 19:08 Permalink Suggest to check the Percent Suggest to check the Percent Type of Activities. It must be Physical.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2014-12-16 13:42 Permalink where did you get the excel where did you get the excel file that you are importing ? create an excel file to populate with your updated information by exporting the fields that you want this give you a template. also go to the project mode big button on the left and make sure that you projetc is highlighted click on the calculations tab on the left make sure that Activity Percent complete based on activity steps is NOT checked
Member for
15 years 11 monthsSuggest to check the Percent
Suggest to check the Percent Type of Activities. It must be Physical.
Member for
16 years 3 monthswhere did you get the excel
where did you get the excel file that you are importing ?
create an excel file to populate with your updated information by exporting the fields that you want this give you a template.
also go to the project mode big button on the left and make sure that you projetc is highlighted
click on the calculations tab
on the left make sure that Activity Percent complete based on activity steps is NOT checked