ERROR while importing progress from excel

Member for

15 years 11 months

Suggest to check the Percent Type of Activities. It must be Physical.

Member for

16 years 3 months

where did you get the excel file that you are importing  ?

create an excel file to populate with your updated information by exporting the fields that you want this give you a template.

also go to the project mode big button on the left and make sure that you projetc is highlighted 

click on the calculations tab 

on the left make sure that Activity Percent complete based on activity steps is NOT checked