Oild and Gas Construction works - guideline for calculating the rate of work

Member for

10 years 11 months

Dear All,

Thank you for your reply. I understand that I can get the production rates reference from PP Rates.

I checked under the rates section , but I didn't see the production rates there.

For sure I am not looking at the correct location. Is it the correct section to look for?

Can you please send me the link?

 

Many thanks in advance.

Cheers!!!

 

- Joe

Member for

10 years 11 months

Dear All,

Thank you for your reply. I understand that I can get the production rates reference from PP Rates.

I checked under the rates section , but I didn't see the production rates there.

For sure I am not looking at the correct location. Is it the correct section to look for?

Can you please send me the link?

 

Many thanks in advance.

Cheers!!!

 

- Joe

Member for

14 years 11 months

Hi Joe,

Calculate the manhour requirement for each activities and accordingly fix the duration.

PP Rates will be useful for manhour calculations.

Best Regards,

 

Sunil.

Member for

15 years 9 months

Hi Joe

Easy question difficult answer.

I am planning to develop a website "Estimating for Planners".  I know that your question is applicable to many planners and schedulers. 

Next summer it is planned for release. 

Regards Johannes