Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2014-09-08 10:18 Permalink Hi RaminYou obviously know Hi Ramin You obviously know more about the subject than I do so just put things in your programme in the order that they have to be carried out and link them logically - Finish > Start. Best regards Mike Testro Member for 13 years 6 months Member for 13 years 6 months Submitted by ramin8174 on Mon, 2014-09-08 07:31 Permalink Thanks, But it needs also Thanks, But it needs also environmental, land clearance, structure plan, development plan and etc, how do we make for these items a project phase. Regards Ramin Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2014-09-03 17:25 Permalink Hi RaminThis will do for both Hi Ramin This will do for both design and construction on a green field site. Survey Site clearance > take out old services - divert live > clear contamination Earthworks > cut fill to profiles Infrastrure > roads > drains > services > sub stations Structures in phases Landscaping > planting > water features Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2014-09-08 10:18 Permalink Hi RaminYou obviously know Hi Ramin You obviously know more about the subject than I do so just put things in your programme in the order that they have to be carried out and link them logically - Finish > Start. Best regards Mike Testro
Member for 13 years 6 months Member for 13 years 6 months Submitted by ramin8174 on Mon, 2014-09-08 07:31 Permalink Thanks, But it needs also Thanks, But it needs also environmental, land clearance, structure plan, development plan and etc, how do we make for these items a project phase. Regards Ramin
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2014-09-03 17:25 Permalink Hi RaminThis will do for both Hi Ramin This will do for both design and construction on a green field site. Survey Site clearance > take out old services - divert live > clear contamination Earthworks > cut fill to profiles Infrastrure > roads > drains > services > sub stations Structures in phases Landscaping > planting > water features Best regards Mike Testro
Member for
19 years 10 monthsHi RaminYou obviously know
Hi Ramin
You obviously know more about the subject than I do so just put things in your programme in the order that they have to be carried out and link them logically - Finish > Start.
Best regards
Mike Testro
Member for
13 years 6 monthsThanks, But it needs also
Thanks,
But it needs also environmental, land clearance, structure plan, development plan and etc, how do we make for these items a project phase.
Regards
Ramin
Member for
19 years 10 monthsHi RaminThis will do for both
Hi Ramin
This will do for both design and construction on a green field site.
Survey
Site clearance > take out old services - divert live > clear contamination
Earthworks > cut fill to profiles
Infrastrure > roads > drains > services > sub stations
Structures in phases
Landscaping > planting > water features
Best regards
Mike Testro