Hi Mike, Thanks. Been trying to delete the 2 posts but cannot find the option. I've been given the duration already for the aforementioned tasks. What I'm after are the processes/activities involved in EPC bidding. Do you have sample schedule either in p6 or MS project that I can refer?
Member for
12 years 4 monthsHi Mike, Thanks. Been trying
Hi Mike, Thanks. Been trying to delete the 2 posts but cannot find the option. I've been given the duration already for the aforementioned tasks. What I'm after are the processes/activities involved in EPC bidding. Do you have sample schedule either in p6 or MS project that I can refer?
If in case, can you kindly email at this id? wally.casuga@gmail.com
Regards,
Wally
Member for
19 years 10 monthsHi Wally - welcome to
Hi Wally - welcome to planning planet - next time only hit the "save" button once.
The basic principle of a bid tender is to see if the work can be completed in the stated contract period.
Do not try to squeeze durations to make it fit - that is for the bid manager to decide after he has all the facts.
So make sure your durations and logic is correct - particularly with the Engineering / Procurement sections.
Work at level 4 with FS links.
Make sure that the Employer's deliverables are set with clear milestones linked ALAP to the Contractor's task.
Best regards
Mike Testro