Bidding Schedule for EPC

Member for

12 years 4 months

Hi Mike, Thanks. Been trying to delete the 2 posts but cannot find the option. I've been given the duration already for the aforementioned tasks. What I'm after are the processes/activities involved in EPC bidding. Do you have sample schedule either in p6 or MS project that I can refer?

If in case, can you kindly email at this id? wally.casuga@gmail.com

Regards,

Wally

Member for

19 years 10 months

Hi Wally - welcome to planning planet - next time only hit the "save" button once.

The basic principle of a bid tender is to see if the work can be completed in the stated contract period.

Do not try to squeeze durations to make it fit - that is for the bid manager to decide after he has all the facts.

So make sure your durations and logic is correct - particularly with the Engineering / Procurement sections.

Work at level 4 with FS links.

Make sure that the Employer's deliverables are set with clear milestones linked ALAP to the Contractor's task.

Best regards

Mike Testro