Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sun, 2014-07-13 20:20 Permalink Hi PaulWelcome to Planning Hi Paul Welcome to Planning Planet. By definition a milestone has zero duration. If you add a duration it becomes a task. Best regards Mike Testro. Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sun, 2014-07-13 20:20 Permalink Hi PaulWelcome to Planning Hi Paul Welcome to Planning Planet. By definition a milestone has zero duration. If you add a duration it becomes a task. Best regards Mike Testro.
Member for
19 years 10 monthsHi PaulWelcome to Planning
Hi Paul
Welcome to Planning Planet.
By definition a milestone has zero duration.
If you add a duration it becomes a task.
Best regards
Mike Testro.