Planning, Scheduling & Programming Discussion Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Tue, 2014-06-24 10:18 Permalink Your schedule needs to be Your schedule needs to be cost loaded for progress to roll-up to WBS level. Assign cost to the new activities and their WBS will display performance & schedule % completes. Log in or register to post comments
Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Tue, 2014-06-24 10:18 Permalink Your schedule needs to be Your schedule needs to be cost loaded for progress to roll-up to WBS level. Assign cost to the new activities and their WBS will display performance & schedule % completes.
Member for
21 years 9 monthsYour schedule needs to be
Your schedule needs to be cost loaded for progress to roll-up to WBS level.
Assign cost to the new activities and their WBS will display performance & schedule % completes.