If your CL14 programme is saved as the Project Baseline, and your last period programme is saved as the Primary Baseline, then just insert the existing columns "Variance - BL Project Finish Date" and "Variance - BL1 Finish Date" (found in the durations group)
Then you can edit the column titles to mention CL14 and last period
No need to mess about with custom fields and formulaes.
Member for
13 years 1 monthGary, You are the best and a
Gary,
You are the best and a genius.
Thank you very much.
Regards,
Patrick
Member for
16 years 7 monthsPatrick, If your CL14
Patrick,
If your CL14 programme is saved as the Project Baseline, and your last period programme is saved as the Primary Baseline, then just insert the existing columns "Variance - BL Project Finish Date" and "Variance - BL1 Finish Date" (found in the durations group)
Then you can edit the column titles to mention CL14 and last period
No need to mess about with custom fields and formulaes.