Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2013-08-27 21:18 Permalink Hi ThomasYou should at least Hi Thomas You should at least have a baseline programme that shows the key milestones that the stakeholders have to meet. If you have no idea what they are just do what everyone else does and throw in some dates that look to be achievable. That is what "top down" planning is all about. Be the King of the Wingers. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2013-08-27 21:18 Permalink Hi ThomasYou should at least Hi Thomas You should at least have a baseline programme that shows the key milestones that the stakeholders have to meet. If you have no idea what they are just do what everyone else does and throw in some dates that look to be achievable. That is what "top down" planning is all about. Be the King of the Wingers. Best regards Mike Testro
Member for
19 years 10 monthsHi ThomasYou should at least
Hi Thomas
You should at least have a baseline programme that shows the key milestones that the stakeholders have to meet.
If you have no idea what they are just do what everyone else does and throw in some dates that look to be achievable.
That is what "top down" planning is all about.
Be the King of the Wingers.
Best regards
Mike Testro