Planning, Scheduling & Programming Discussion Member for 12 years 3 months Member for 12 years 3 months Submitted by Leonard Esber on Fri, 2013-07-19 11:07 Permalink Thank you very much. But Thank you very much. But this is what happened I did...from menu bar, I clicked TOOLS then OPTIONS then VIEW tab. Under Outline options for '(project name)' I checked the box Show project summary tasks then the uppermost row appeared. Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Fri, 2013-07-19 10:32 Permalink To Options, go to the Project To Options, go to the Project Options and display the Project Summary bars, or add the bar by creating a summary bar. Regards Paul E Harris BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner Managing Director and President Eastwood Harris Pty Ltd, Australia www.eh.com.au, www.eastwoodharris.com, www.primaskills.com.au and www.primavera.com.au Project Control Consultants and Planning and scheduling software book and training material publishers Log in or register to post comments
Member for 12 years 3 months Member for 12 years 3 months Submitted by Leonard Esber on Fri, 2013-07-19 11:07 Permalink Thank you very much. But Thank you very much. But this is what happened I did...from menu bar, I clicked TOOLS then OPTIONS then VIEW tab. Under Outline options for '(project name)' I checked the box Show project summary tasks then the uppermost row appeared.
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Fri, 2013-07-19 10:32 Permalink To Options, go to the Project To Options, go to the Project Options and display the Project Summary bars, or add the bar by creating a summary bar. Regards Paul E Harris BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner Managing Director and President Eastwood Harris Pty Ltd, Australia www.eh.com.au, www.eastwoodharris.com, www.primaskills.com.au and www.primavera.com.au Project Control Consultants and Planning and scheduling software book and training material publishers
Member for
12 years 3 monthsThank you very much. But
Thank you very much. But this is what happened I did...from menu bar, I clicked TOOLS then OPTIONS then VIEW tab. Under Outline options for '(project name)' I checked the box Show project summary tasks then the uppermost row appeared.
Member for
24 years 6 monthsTo Options, go to the Project
To Options, go to the Project Options and display the Project Summary bars, or add the bar by creating a summary bar.
Regards
Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
www.eh.com.au, www.eastwoodharris.com, www.primaskills.com.au and www.primavera.com.au
Project Control Consultants and Planning and scheduling software book and training material publishers