Missing Row when P6 Exported to MS Project

Member for

12 years 3 months

Thank you very much.  But this is what happened I did...from menu bar, I clicked TOOLS then OPTIONS then VIEW tab.  Under Outline options for '(project name)' I checked the box Show project summary tasks then the uppermost row appeared.

Member for

24 years 6 months

To Options, go to the Project Options and display the Project Summary bars, or add the bar by creating a summary bar.

Regards

Paul E Harris

BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner

Managing Director and President

Eastwood Harris Pty Ltd, Australia

www.eh.com.auwww.eastwoodharris.com, www.primaskills.com.au  and www.primavera.com.au

Project Control Consultants and Planning and scheduling software book and training material publishers