Although you are alerted in each case, be aware of the following constraints when creating or configuring financial periods:
You cannot introduce gaps in a series of financial periods. Any new periods you create must start or end flush with any existing entries. For example, if October 7-13 and October 14-20 are existing financial periods, you can create a new one that either ends on October 6 or starts on October 21.
You cannot overlap financial periods. In order to serve their purpose, financial periods must represent unique slices of time.
You can create financial periods with a duration of fewer than seven days (one week); however, you cannot view them in timescales in P6. Use P6 Professional if you need to view data by financial periods spanning increments of fewer than seven days (one week).
I wonder how you would report on a specific slice that do not fall within the pre-defined periods for purposes like analyzing "the measured mile" on actual slices for work that happened on slices different than your pre-defined financial periods. Here some sort of project truncation is in order and must be accurate if to be presented in court.
Spider Project truncation is one of the report forms executed for a certain period and presented in a separate project form. In project truncation, project data and representations are all displayed, also data under charges of cost components and materials, duration, volume, and also cost and materials calculation for the set time period are automatically executed.
Your truncations got to follow true actual distributions.
Good luck.
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Fri, 2013-03-08 08:46
Those restrictions only apply if you are trying to "Batch Create" your financial periods -you can manually add each period with whatever dates you like by using the "add" option on the right hand side of the financial periods window
Thx for you answer. That was my first try as well but here is the problem:
P6 allows you to define on what day the week ends and what month your year ends, but this is not an option if you want monthly outputs. It uses first and last day of the month by default.
@ Rafael: Client imposes P6, so can't change to your Spider Software.
Best Regards,
Gert
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Thu, 2013-03-07 13:23
Only one global set of financial periods for all jobs is allowed. As a workaround you can define separate databases for every financial periods set.
Updating shall match financial periods for it to work as intended.
It is important you understand how P6 distribute quantities on started but unfinished activities, always changing, a real mess that requires the use of pre-defined financial periods.
You can switch to software that will get it right, without the issue on changing quantities that span between several financial periods. In Spider Project you do not need to define financial periods as every update represent a financial period and therefore the distributions are fixed upon every update. For your reporting you can define as many custom periods you need to.
I suppose other software shall be able to get your reporting periods with the right quantities on past performance without requiring pre-defined financial periods and without the annoyance of the requirement for updates matching your pre-defined financial periods.
Good luck.
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Thu, 2013-03-07 12:29
Member for
12 years 8 monthsGary,That's the trick! Thank
Gary,
That's the trick! Thank you for your help. I like easy solutions.
Rafael,
Thx for your comments, they are very useful and I'll keep them in mind.
Best Regards,
Gert
Member for
21 years 8 monthsFrom,
From, http://docs.oracle.com/cd/E17266_01/p6help/help/en/helpmain.htm?toc.htm?21452.htm
Although you are alerted in each case, be aware of the following constraints when creating or configuring financial periods:
I wonder how you would report on a specific slice that do not fall within the pre-defined periods for purposes like analyzing "the measured mile" on actual slices for work that happened on slices different than your pre-defined financial periods. Here some sort of project truncation is in order and must be accurate if to be presented in court.
Spider Project truncation is one of the report forms executed for a certain period and presented in a separate project form. In project truncation, project data and representations are all displayed, also data under charges of cost components and materials, duration, volume, and also cost and materials calculation for the set time period are automatically executed.
Your truncations got to follow true actual distributions.
Good luck.
Member for
16 years 7 monthsHi Gert, Those restrictions
Hi Gert,
Those restrictions only apply if you are trying to "Batch Create" your financial periods -you can manually add each period with whatever dates you like by using the "add" option on the right hand side of the financial periods window
Cheers,
G
Member for
12 years 8 monthsHi Gary,Thx for you answer.
Hi Gary,
Thx for you answer. That was my first try as well but here is the problem:
P6 allows you to define on what day the week ends and what month your year ends, but this is not an option if you want monthly outputs. It uses first and last day of the month by default.
@ Rafael: Client imposes P6, so can't change to your Spider Software.
Best Regards,
Gert
Member for
21 years 8 monthsSome of the issues with P6
Some of the issues with P6 financial periods are:
It is important you understand how P6 distribute quantities on started but unfinished activities, always changing, a real mess that requires the use of pre-defined financial periods.
You can switch to software that will get it right, without the issue on changing quantities that span between several financial periods. In Spider Project you do not need to define financial periods as every update represent a financial period and therefore the distributions are fixed upon every update. For your reporting you can define as many custom periods you need to.
I suppose other software shall be able to get your reporting periods with the right quantities on past performance without requiring pre-defined financial periods and without the annoyance of the requirement for updates matching your pre-defined financial periods.
Good luck.
Member for
16 years 7 monthsHi Gert, You should be able
Hi Gert,
You should be able to do this with financial periods.
I've not done it myself before, but if you go to Admin > financial periods, you can manually create periods running 21st to 20th
Then in the timesclaes window, you can select "fiscal" option for primary dates, and organise your timescales by financial period.
Standard resource reports should then be presented using these periods.
Cheers,
G
Member for
19 years 10 monthsHi Gert You can run a filter
Hi Gert
You can run a filter between two dates to generate a look ahead programme.
This can be combined with you resource filter.
Best regards
Mike Testro
Member for
12 years 8 monthsHi Gary,Using Primavera P6
Hi Gary,
Using Primavera P6 v8.2.1
Member for
16 years 7 monthsGert, It would help if we
Gert,
It would help if we knew what software you were using?
Member for
12 years 8 monthsThanx Mike,Good to be
Thanx Mike,
Good to be here!
Can you explain me what you understand under 'time slice report' and how I can generate it?
Thx,
Gert
Member for
19 years 10 monthsHi Gert Welcome to planning
Hi Gert
Welcome to planning planet.
Filter on theresource and generate a time slice report.
Best regards
Mike Testro