Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2013-01-28 11:18 Permalink Hi Yaser Linking from a Hi Yaser Linking from a milestone the same calendar rules apply - otherwise the is no difference. Best regards Mike Testro Member for 15 years 5 months Member for 15 years 6 months Submitted by Yaser A. Al-Bustanji on Mon, 2013-01-28 10:23 Permalink Thanks but my question about Thanks but my question about the effect of this relations when the predecessors is milestone (Zero Duration) in p3 or Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2013-01-28 08:59 Permalink Hi Yaser A SS Link will start Hi Yaser A SS Link will start at the start of the predecessor task and a FS will link come from the end of the predecessor. In Asta PowerProject a FS/SS link will take on the calendar of the predecessor but a FF link will use the successor calendar. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2013-01-28 11:18 Permalink Hi Yaser Linking from a Hi Yaser Linking from a milestone the same calendar rules apply - otherwise the is no difference. Best regards Mike Testro
Member for 15 years 5 months Member for 15 years 6 months Submitted by Yaser A. Al-Bustanji on Mon, 2013-01-28 10:23 Permalink Thanks but my question about Thanks but my question about the effect of this relations when the predecessors is milestone (Zero Duration) in p3 or
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2013-01-28 08:59 Permalink Hi Yaser A SS Link will start Hi Yaser A SS Link will start at the start of the predecessor task and a FS will link come from the end of the predecessor. In Asta PowerProject a FS/SS link will take on the calendar of the predecessor but a FF link will use the successor calendar. Best regards Mike Testro
Member for
19 years 10 monthsHi Yaser Linking from a
Hi Yaser
Linking from a milestone the same calendar rules apply - otherwise the is no difference.
Best regards
Mike Testro
Member for
15 years 5 monthsThanks but my question about
Thanks but my question about the effect of this relations when the predecessors is milestone (Zero Duration) in p3 or
Member for
19 years 10 monthsHi Yaser A SS Link will start
Hi Yaser
A SS Link will start at the start of the predecessor task and a FS will link come from the end of the predecessor.
In Asta PowerProject a FS/SS link will take on the calendar of the predecessor but a FF link will use the successor calendar.
Best regards
Mike Testro