Negative (?) terminal float

Member for

19 years 1 month

1. Yes - can be due to any delay;

2. Yes - by crashing your schedule, adding resources or whatever

you can also see delays if you got negative floats

Member for

13 years 11 months

Think I might have overcomplicated the issue. So I should try to simplify:

1 - Can the PCD be after the CD further to for instance contractor's caused delay?

2-  Can the PCD ever be brought back to be before the CD?

 

 

 

 

Member for

15 years

I think there is some constraint on the Critical path (Madatory finish for exemple) this why you don't see this delay on the end or the delay is on an activities wich have more than three weeks float.

 

You should chek your activities wiche have contraints first (make it free), chek the activities TF...

 

Regards.

Ahmed

Member for

16 years 7 months

Emmaunelle,

 

You say there is a delay, but you also say that the current programme doesn't show the delay -please explain

Member for

13 years 11 months

... If there is a 3 week delay and 2 weeks of that delay are absorbed by TRA, then there must be a net 1 week delay. Why does the current programme not show this delay?

So what should tbe the PCD/CD dates if original PCD = CD = 13/08/12.

Member for

16 years 7 months

Now I am confused...

If there is a 3 week delay and 2 weeks of that delay are absorbed by TRA, then there must be a net 1 week delay. Why does the current programme not show this delay?

Is it perhaps because the 3 week delay occured on an activity that was not on the critical path -ie only completion of that activity and not the whole project has been delayed?

 

If the client delays the project, then this should trigger a CE which ammends the completion date by the full three weeks. -TRA and terminal float belong to the contractor only -they can not be used to reduce a contractor's entitlement to EOT.

 

The only references I use for NEC contracts are the guidance notes that accompany the standard contract form. I can't recommend a book or anything.

Member for

13 years 11 months

OK thanks.

Delay was contractor's responsibility so you advise "planned completion date + 1 week and same completion date"
Concern I have is that the programme does not "show" delay i.e. current completion date same as initial completion date in contracts data vol.1.

Also, not understanding, should this be the client responsibility, why the PCD and CD move by the amount of weeks you said.

Can you suggest any papers/books... that would help in getting a better grasp on PCD, CD and terminal float.

E.

 

 

Member for

16 years 7 months

If the delay was the responsibility of the contractor (ie no CE), then:

planned completion date + 1 week and same completion date

 

If the delay was the responsibility of the client, then:

planned completion date + 1 week and completion date + 3 weeks

 

Cheers,

G