Planning, Scheduling & Programming Discussion Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Wed, 2012-08-08 12:25 Permalink Melissa, The early dates of Melissa, The early dates of your Baseline or Initial Schedule represents the Planned.Use the Baseline to generate the required curve. Member for 14 years 4 months Member for 14 years 4 months Submitted by mofazus86 on Wed, 2012-08-08 05:05 Permalink Go to resource graph on the Go to resource graph on the task bar in P6. Then right click on the graph to customize according to what you want. Log in or register to post comments
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Wed, 2012-08-08 12:25 Permalink Melissa, The early dates of Melissa, The early dates of your Baseline or Initial Schedule represents the Planned.Use the Baseline to generate the required curve.
Member for 14 years 4 months Member for 14 years 4 months Submitted by mofazus86 on Wed, 2012-08-08 05:05 Permalink Go to resource graph on the Go to resource graph on the task bar in P6. Then right click on the graph to customize according to what you want.
Member for
15 years 11 monthsMelissa, The early dates of
Melissa,
The early dates of your Baseline or Initial Schedule represents the Planned.
Use the Baseline to generate the required curve.
Member for
14 years 4 monthsGo to resource graph on the
Go to resource graph on the task bar in P6. Then right click on the graph to customize according to what you want.