Generating an Early, Late, & Planned Curve in P6

Member for

15 years 11 months

Melissa,

The early dates of your Baseline or Initial Schedule represents the Planned.
Use the Baseline to generate the required curve.

Member for

14 years 4 months

Go to resource graph on the task bar in P6. Then right click on the graph to customize according to what you want.