Planning guide for re-measured contract

Member for

14 years 7 months

Hi Mervilyne, 

 

The baseline schedule should always remain as per the contract quantities. What you can do is to just change your remaining hence at completion which would show your forecast is much more/less than the baseline. You can choose to measure your performance either with the baseline or forecast subject to you agreeing with the client.

 

 

Cheers,

 

Adrian N

Member for

13 years 11 months

Hi Mervilyne,

 

As its a re-measure can you not just enter actuals? I am assuming the re-measure is done after the work and not during or before? if it is before or during re-measure can you not increase the qty on the schedule then once a month or whenever your progress has been agreed re baseline the works with the re-measured qtys.

I wouldn't delete any activity I would set them to have Zero units etc as deleted activities show when using claim digger and could look like your trying to hide something.

 

regards

Ryan