Imran, I will recommend that you read the drawings (especially, GA, Plan and Profiles, coordination drawings). Talk or consult with your construction managers/supervisors on the priorities and sequencing. Plan the program, review it with them, and finalise the plan.
Member for
13 years 10 months
Member for13 years11 months
Submitted by imrankhandsce on Tue, 2012-05-29 17:56
Thanks a lot for your quick reply. Let me proceed accordingly what you have pointed and if i get any difficulty i will definately gonna ask your help again!!!! :)
First divide the layout into sections and then plan to work from the back out towards the entrance.
Next sort out your work sections; Roads - Pavings - services - landscaping etc.
Roads:
The sequence is - Excavate to formation - lay kerbs and edgings - sub base - tarmac base - topping and lines.
These last two being kept to the very end of the project.
Pavings:
After Kerbs and edgings and services the pavement sub base and topping is laid.
Services:
Water gas elecricity It are usually placed in the pavement with tap off connections to the villas.
Street Lighting needs box outs in the pavement for electical connections which are to be filled after testing.
Drains are different because they have to be laid from the lowest outfall up to the highest point - cutting across your sections. If the drains are located in the roads then they must be installed before the sub base.
Road run off drains follow the contour of the kerb.
Landscaping:
Hard landscaping such as paths and parking can be done alongiside Pavings.
Soft landscaping and topsoiling and planting is done last - but planting may have to follow the relevant planting season. Include for cutting and pruning in the next season.
Fencing signs and furniture are placed after the hard landscaping.
If there is a security hut and barrier then put this in a separate sub programme.
Member for
13 years 10 monthsHi Sofi, Thanks for your
Hi Sofi,
Thanks for your suggestion!!!!
Regards,
Imran
Member for
13 years 9 monthsImran, I will recommend that
Imran, I will recommend that you read the drawings (especially, GA, Plan and Profiles, coordination drawings). Talk or consult with your construction managers/supervisors on the priorities and sequencing. Plan the program, review it with them, and finalise the plan.
Member for
13 years 10 monthsHi Mike, Thanks a lot
Hi Mike,
Thanks a lot for your quick reply. Let me proceed accordingly what you have pointed and if i get any difficulty i will definately gonna ask your help again!!!! :)
Regards,
Imran
Member for
19 years 10 monthsHi Imran First divide the
Hi Imran
First divide the layout into sections and then plan to work from the back out towards the entrance.
Next sort out your work sections; Roads - Pavings - services - landscaping etc.
Roads:
The sequence is - Excavate to formation - lay kerbs and edgings - sub base - tarmac base - topping and lines.
These last two being kept to the very end of the project.
Pavings:
After Kerbs and edgings and services the pavement sub base and topping is laid.
Services:
Water gas elecricity It are usually placed in the pavement with tap off connections to the villas.
Street Lighting needs box outs in the pavement for electical connections which are to be filled after testing.
Drains are different because they have to be laid from the lowest outfall up to the highest point - cutting across your sections. If the drains are located in the roads then they must be installed before the sub base.
Road run off drains follow the contour of the kerb.
Landscaping:
Hard landscaping such as paths and parking can be done alongiside Pavings.
Soft landscaping and topsoiling and planting is done last - but planting may have to follow the relevant planting season. Include for cutting and pruning in the next season.
Fencing signs and furniture are placed after the hard landscaping.
If there is a security hut and barrier then put this in a separate sub programme.
Best regards
Mike Testro