Hi,

The discripancies maybe due to the wrong Planned Dates and/or the assigned Baseline.

 

As an advice..... When intends to Make a New Program as Baseline, do note of the following..

1. Make sure the Project Planned Start = Data Date
2. Make sure that all Activities Planned Start = Early Start = Start
3. Make sure that all Acitivites Planned Finish = Early Finish = Finish

Then the same program shall be used as the current program for monitoring.

Member for

24 years

Sunil,

check the details and see what is pushing that variance to -212d delay, it may just be accidental error in your update.