The discripancies maybe due to the wrong Planned Dates and/or the assigned Baseline.
As an advice..... When intends to Make a New Program as Baseline, do note of the following..
1. Make sure the Project Planned Start = Data Date 2. Make sure that all Activities Planned Start = Early Start = Start 3. Make sure that all Acitivites Planned Finish = Early Finish = Finish
Then the same program shall be used as the current program for monitoring.
Member for
24 years
Member for24 years1 month
Submitted by Daniel Limson on Mon, 2012-05-07 09:24
Member for
15 yearsHi Daniel,Thanks for
Hi Daniel,
Thanks for reply.
Sunil
Member for
15 yearsHi Raymund,Thanks for your
Hi Raymund,
Thanks for your reply.
Regards
Sunil
Member for
15 years 11 monthsHi, The discripancies maybe
Hi,
The discripancies maybe due to the wrong Planned Dates and/or the assigned Baseline.
As an advice..... When intends to Make a New Program as Baseline, do note of the following..
1. Make sure the Project Planned Start = Data Date
2. Make sure that all Activities Planned Start = Early Start = Start
3. Make sure that all Acitivites Planned Finish = Early Finish = Finish
Then the same program shall be used as the current program for monitoring.
Member for
24 yearsSunil,check the details and
Sunil,
check the details and see what is pushing that variance to -212d delay, it may just be accidental error in your update.